Penske Off-Highway Engineering - Design Change Request (DCR)
A DCR should be summitted if any
changes with the initial scope have changed on the project. If there are major
changes to a project compared to the initial submitted RFES, a new RFES form should
instead be summited. A DCR should only be submitted for minor changes.
If a Penske Off-highway drawing
needs to be modified after Revision A, a DCR should be completed. This DCR will
detail all the required changes on the drawing, why the changes are required,
the date it was to be modified and the person requesting the DCR. Once the DCR
is submitted, the revision table on the drawing should refer to the relevant
DCR number. A copy of the DCR should also be saved in PDF and placed in the
project folder on PDM.
The link to lodge a DCR is on The
Podium.
Fill in each field with all the relevant information. Once
you have submitted the DCR, this is now saved on monday.com.
When you have opened monday.com,
click on the ‘DCR tab’ on the left side. This will open all the DCR’s which have
been submitted. Click the ‘main table’ tab at the top of the page. Once you
have found the relevant DCR, you can see the DCR ID number which monday.com has
generated and assigned. This is the unique DCR ID number. Refer to this number
in your drawing revision table.
Once a DCR has been submitted, a
PDF version of the DCR should be saved in the project folder on PDM. To save a
pdf version, click the DCR tab on the left tab. Search for the DCR and once
found, click the pdf export button on the top. Save this pdf in the project
folder.
Related Articles
Penske Off-Highway Engineering Drawing Guide
When drawings are created and approved for the first time (Revision A), they should have the following comments to confirm that the drawings are approved. · Part drawing Revision A description: RELEASED FOR MANUFACTURE · Assembly Drawing Revision A ...
Drawing Revision Triangle
After each revision change on a Penske Off-Highway Engineering drawing, a description of the changes required are to be recorded in the revision table. A Design Change Request (DCR) may be required if the change is major. To make the changes easier ...
Liebherr 9800 Engine change out document.
TSD 17-05 is a step by step procedure that has been put together to aid service technicians to remove and replace the 12V4000C13L engines in a Liebherr 9800 excavator. There is a lot of useful information contained in this guide for example - wiring ...
Mercedes PLD Parameter change request from 24v to 12v - error code SPN 24578 & SPN 155649
In this case, the engine was replaced with one from PPS stock with a similar calibration that was altered for us by MTU on the mainframe.When replacing and trying to match an older engine, the use of a newer "V23" PLD controller requires updating of ...
Extending oil change interval on MTU engines.
As a result of increasing demand from within the industry a oil interval extension procedure has been developed. TSD 16-05 outlines the procedure to establish if an extension on oil change interval is achievable without having detrimental effects on ...