MSP replacement- setting Engine hours correctly

MSP replacement- setting Engine hours correctly

If you can change the parametervalue for engine hours on the MSP, but the new value is not accepted: After you set the correct parametervalue, press two times only the button “SELECT” to get to the next parameter . Now to get out of the configuration menu, press simultaneously the buttons “Digit” + “Cursor” (LED “Test” stops blinking) In the visualization menu from the MSP go to “engine hours”. Simultaneously press the buttons “Select” and “Cursor” for at least 10 s. Now your preset engine hour value must be visible in the visualization from the MSP and IPC.
    • Related Articles

    • Reman OM engine aftertreatment commisioning.

      I.There is a requirement for Reman OM engines with aftertreatment systems sold through Penske AUNZ to have the aftertreatment system commissioned by RRPS / MTU. This is completed via VDOK and links to the new reman engines serial number to the ACM, ...
    • Liebherr 9800 Engine change out document.

      TSD 17-05 is a step by step procedure that has been put together to aid service technicians to remove and replace the 12V4000C13L engines in a Liebherr 9800 excavator. There is a lot of useful information contained in this guide for example - wiring ...
    • Engine Application – Cyclic Loading

      Background: Many diesel engine applications involve loading/unloading, think an on-highway truck going up and down hilly terrain (see country road), but specific applications are highly cyclic, passenger rail car and transit/city bus are two specific ...
    • Alignment procedure for alternator to engine

      Alternator manufacturer alignment procedure in the attached documents.
    • Hitachi EX3600 Engine change out guide.

      TSD 11-08 REV3 has been developed to assist service technicians to remove and replace a 16V4000E20R engine in a Hitachi EX3600 excavator.