Penske Off-Highway Engineering Drawing Guide

Penske Off-Highway Engineering Drawing Guide

When drawings are created and approved for the first time (Revision A), they should have the following comments to confirm that the drawings are approved.

·         Part drawing Revision A description:

                RELEASED FOR MANUFACTURE 

·        Assembly Drawing Revision A description:

                RELEASED FOR REFERENCE ONLY

 

Below is an example of how a typical Penske off-highway engineering drawing should look like. Comments are shown in each field and where to input the information.



A convenient guide for Geometric Dimensioning and Tolerancing (GD&T) symbols can be found in the following website.

    • Related Articles

    • Drawing Revision Triangle

      After each revision change on a Penske Off-Highway Engineering drawing, a description of the changes required are to be recorded in the revision table. A Design Change Request (DCR) may be required if the change is major. To make the changes easier ...
    • Penske Off-Highway Engineering - Design Change Request (DCR)

      A DCR should be summitted if any changes with the initial scope have changed on the project. If there are major changes to a project compared to the initial submitted RFES, a new RFES form should instead be summited. A DCR should only be submitted ...
    • Hitachi EX3600 Engine change out guide.

      TSD 11-08 REV3 has been developed to assist service technicians to remove and replace a 16V4000E20R engine in a Hitachi EX3600 excavator. 
    • Technicians Guide LPR_HDEP Cylinder Kit Failure

      Technicians Guide LPR_HDEP Cylinder Kit Failure
    • MTU drawing No: 0182504901

      MTU Drawing # 0182504901 has a typo error with the labeling of the coupling to flange bolts. Use Geislinger drawing # G001152E which has the correct labeling of all bolts. MTU drawing based on this.